E0A04 : When evaluating a site with multiple transmitters operating at the same time, the operators and licensees of which transmitters are responsible for mitigating over-exposure situations?
A
Each transmitter that produces 20 percent or more of its MPE limit in areas where the total MPE limit is exceeded
B
Each transmitter operating with a duty cycle greater than 25 percent
C
Each transmitter that produces 5 percent or more of its MPE limit in areas where the total MPE limit is exceeded
D
Each transmitter operating with a duty cycle greater than 50 percent
Correct Answer: Each transmitter that produces 5 percent or more of its MPE limit in areas where the total MPE limit is exceeded